(Solved): Question 18 5 Pts Jim Is Managing An Airport Construction Project And Currently Sequencing The Proje...
Question 18 5 pts Jim is managing an airport construction project and currently sequencing the project activities and defining their logical relationships. Two activities have both the Start-Start and Finish-Finish relationships. How should Jim schedule these activities? 0 Select the FF relationship as this cna help meet the project deadlines. O Apply both the relationships. O Select the SS relationship as this is more logical than the FF relationship. O Select the relationship with the highest impact.
We have an Answer from Expert
View Expert Answer
Expert Answer
Select the SS relationship this is more logical than than the FF relationship asin which a Successor Activity is not able to start until
We have an Answer from Expert
Buy This Answer $6
Buy This Answer $6
-- OR --
Subscribe To View Unlimited Answers
Subscribe $20 / Month
Subscribe $20 / Month